Project Milestones
May - August 2024
- Preparation of contract documents
August - September 2024
- Project tender and procurement
October 2024
- Proposed drawings finalized. Review them here [PDF 293 kb]
- The last day the Isabel Turner Branch will be open is October 24, 2024
November 2024
- The temporary Cataraqui Centre Branch opened on November 1, 2024, at the Cataraqui Centre
Early 2026
- Projected completion date
Spring 2026
- Projected Isabel Turner Branch re-opening