Isabel Turner Branch Renovations

Project Schedule and Budget

Project Milestones 

May -  August 2024

  • Preparation of contract documents 

August - September 2024

  • Project tender and procurement

October 2024

  • The last day the Isabel Turner Branch will be open is October 24, 2024

November 2024

  • The temporary Cataraqui Centre Branch will open on November 1, 2024, at the Cataraqui Centre 

Early 2026

  • Projected completion date

Spring 2026

  • Projected Isabel Turner Branch re-opening  

Budget

The construction budget is expected to be approximately $4.9 million, $300,000 has been budgeted to cover temporary space, leasehold improvements and relocation costs. Funding for furniture, shelving and other equipment will be requested from the City as part of the Library’s 2025 budget request.