Isabel Turner Branch Renovations

Project Schedule and Budget

Project Milestones 

May -  August 2024

  • Preparation of contract documents 

August - September 2024

  • Project tender and procurement

Fall 2024

  • Projected construction start date
  • Relocation to temporary space at the Cataraqui Centre 

Fall/Winter 2025

  • Projected completion date

Early 2026

  • Isabel Turner Branch re-opening  

Budget

The construction budget is expected to be approximately $4.9 million, $300,000 has been budgeted to cover temporary space, leasehold improvements and relocation costs. Funding for furniture, shelving and other equipment will be requested from the City as part of the Library’s 2025 budget request.